Home >  Alternative Construction Technologies >  Panelized Home Building >  Foundation to framed house photo essay

On-Home-Site  Panelization Process

From Foundation to a Framed Home in 9 Hours

Photos Courtesy of
Harvest Homes
On-Site Home Panelization Process
7:00 House raising day has come
First floor deck
7:30 lifting over 1st floor deck
First floor walls
9:00 1st floor deck set, craning over 1st floor walls
     
First floor exterior walls
9:10 Setting 1st floor exterior walls
Interior walls
11:30 Setting interior walls
Second floor deck
1:00 Craning up 2nd floor deck
     
Second floor deck
1:10 Preparing to set 2nd floor deck

Second floor deck
1:20 Setting 2nd floor deck
Second floor exterior walls
2:30 Setting 2nd floor exterior walls
     
Connecting exterior walls
Placing connecting exterior walls
Second floor interior walls
3:00 Craning in 2nd floor interior walls
Garage walls
4:00 Setting garage walls
     
Roof trusses
Craning up roof trusses
Roof trusses
5:00 Placing roof trusses
 

 

 

OTHER RESOURCES

 

Harvest Homes- Website

 

NAHB - Building Systems Council

 

 

 

Updated: Friday, March 28, 2014 8:30 AM

"Design Basics values its intellectual property and that of its many collaborative partnerships. We therefore will protect our 1,800 + plan design copyrights from illegal infringements. This preserves and maximizes customers' investments, while also protecting its assets, employees and shareholders." 
Member National Association of Home Builders
We are a memeber of the American Institute of Building Design See Design Basics in booth C2850 at the 2015 International Builders Show

See Design Basics in booth 408 at the 2015 Great Lakes Builder Show